Current:Home > reviewsCoast Guard Plan to Build New Icebreakers May Be in Trouble -ChatGPT
Coast Guard Plan to Build New Icebreakers May Be in Trouble
View
Date:2025-04-27 19:28:48
As the Coast Guard and Navy prepare to invest nearly $10 billion in new heavy polar icebreakers, the Government Accountability Office has found problems in key areas of the plan, which it warns could put the program at risk of failure.
In a report released Tuesday, the GAO said the Coast Guard “did not have a sound business case” and may have underestimated both the costs and the amount of time it would take to deliver the ships. Those shortcomings could pose significant risk to the program’s success and to the United States’ presence at the poles, considering the U.S. icebreaker fleet is already on borrowed time, with just one heavy polar icebreaker that is years past its projected lifespan.
The report could strike a blow at the progress being made toward acquiring new ships—a decades-long effort that is becoming increasingly important for both security and science as global temperatures rise.
Funding had seemed closer to succeeding than ever before. President Trump asked Congress for $750 million in the coming fiscal year to start the design and procurement of the new ships. But Congress hasn’t approved the spending yet. Among the competing priorities in the Homeland Security budget is the wall he wants along the U.S.-Mexico border.
The GAO report isn’t a death blow. But if the program is to be shoehorned into the budget, its costs will have to be kept under control.
“For those who understand the urgency and the national need for a heavy icebreaker, this will be seen as putting forward a very thoughtful argument, to make sure we’re doing best practices,” said Heather Conley, a senior vice president at the Center for Strategic and International Studies who focuses on the Arctic. “But for those who find these costs so extraordinary, they may want to slow down and keep reviewing the program—which is the reason we don’t have the icebreakers that we need.”
U.S. Has 2 Icebreakers Today, with Critical Roles
The Coast Guard currently has two icebreakers to fulfill its mission at the poles—the Polar Star, a heavy icebreaker built in 1976 with an expected 30-year lifespan, and the Healy, a medium icebreaker that entered service in 2000. A third icebreaker, the Polar Sea, has been out of commission since 2010, but has been used for parts to keep the Polar Star running.
“If we hold these new icebreakers up for a year or two for additional studies, it’s likely to increase the gap where there might not be a U.S. Coast Guard polar icebreaker available,” said Lawson Brigham, a former captain of the Polar Sea and Arctic researcher at the University of Alaska Fairbanks.
The icebreakers are critical to supporting U.S. interests at the poles. In Antarctica, the Polar Star helps ensure scientific stations can be accessed year-round and have the needed supplies. In the Arctic, both ships are used to support science and are available to support oil spill cleanup efforts, search-and-rescue operations in Alaska and enforcing marine laws related to fishing.
GAO’s 4 Areas of Concern about the New Plan
The Coast Guard and Navy, working jointly, have a plan to build three new heavy polar icebreakers, which will cost an estimated $9.8 billion over their lifetimes. According to the GAO, the plan falters in four key areas.
Design: The GAO found, essentially, that the Coast Guard put the cart before the horse, setting out program baselines before it had conducted a preliminary design review. While that is “consistent with DHS’s [Department of Homeland Security] current acquisition policy, it is inconsistent with acquisition based practices,” the GAO found.
Technology: Though the Coast Guard had indicated that it did not need to conduct a technology assessment because other ships have used the same technologies, the GAO found that applying those technologies to new programs or operational environments without a separate assessment could pose an operational risk.
Right now, the Coast Guard’s schedule calls for the awarding of a detail design contract next summer, putting the technology assessment on a tight timeline. Depending on the scope of the project, technology assessments can take a couple of months to a year to complete, and that would need to be done prior to awarding a contract, said Marie Mak, the director of contracting and national security acquisitions for the GAO.
Cost: The GAO found the Coast Guard’s $9.8 billion estimate for the lifetime costs of three ships mostly met best practices, but it fell short in one key area: “They didn’t do any sort of modeling to account for risks,” Mak said.
Schedule: Mak said that this shortcoming was the most significant. The Coast Guard’s estimated schedule for delivering the icebreakers has the first one being completed in 2023, the next in 2025 and the third in 2026, allowing for three years to construct each ship.
“When we looked at 10 recent ship-building programs, only three were constructed in three years or less, and those three were more basic ships,” Mak said. “They were either based on commercial designs or had commercial specifications. Given that we haven’t built a heavy polar icebreaker in 40 years, it screams optimism.”
Though the report cautions that these issues should be rectified prior to committing funds to build the ships, the GAO was not weighing in on what Congress should do. But it could offer an excuse to those in Congress who would rather push off funding the program.
“We have perfected the art of study to avoid taking difficult, high cost decisions,” said Conley, of CSIS. “If we fall back into that trap again, we are not going to be able to maintain access to the poles. That’s the bottom line here.”
veryGood! (11879)
Related
- The company planning a successor to Concorde makes its first supersonic test
- Hollywood penthouse condo sells for $24 million: See inside the luxury space
- Neil Young reunites with Crazy Horse after a decade, performs double encore
- Bucks veteran Patrick Beverley suspended by NBA for throwing ball at fans
- Biden administration makes final diplomatic push for stability across a turbulent Mideast
- Minnesota makes ticket transparency law, cracking down on hidden costs and re-sellers
- ‘Lord of the Rings: The Hunt for Gollum’ in development with Andy Serkis to direct and star
- Authorities make arrest in 2001 killing of Georgia law student who was found dead in a burning home
- Former Danish minister for Greenland discusses Trump's push to acquire island
- 'Altercation' at Drake's Toronto mansion marks third police-involved incident this week
Ranking
- The Grammy nominee you need to hear: Esperanza Spalding
- Police dismantle pro-Palestinian encampment at MIT, move to clear Philadelphia and Arizona protests
- Southern Brazil is still reeling from massive flooding as it faces risk from new storms
- Liam and Olivia are still the most popular US baby names, and Mateo makes his debut on the list
- Federal Spending Freeze Could Have Widespread Impact on Environment, Emergency Management
- Despite revenue downgrade, North Carolina anticipates nearly $1B more in cash
- Jennifer Garner Reveals Why She Thinks She Was “Born to Breed”
- FLiRT COVID variants are now more than a third of U.S. cases. Scientists share what we know about them so far.
Recommendation
Former Danish minister for Greenland discusses Trump's push to acquire island
This Overnight Balm Works Miracles Any Time My Skin Is Irritated From Rosacea, Eczema, Allergies, or Acne
Prince Harry and Meghan Markle Arrive in Nigeria for 3-Day Tour
US consumer sentiment drops to 6-month low on inflation, unemployment fears
Small twin
Did officials miss Sebastian Aho's held broken stick in Hurricanes' goal vs. Rangers?
Indiana-Atlanta highlights: How Caitlin Clark, Fever performed in second preseason game
Leaked PlayStation Store image appears to reveals cover of 'EA Sports College Football 25' game